24H Quote Help

VihoX 100 Ton Round Counterflow FRP Cooling Tower for Co-Extrusion Lines

Description

The First Frame That Handles Real Co-Extrusion Duty

Co-extrusion changes the cooling equation more than most buyers expect, because two extruders, a combining feedblock and a wider calender all reject heat at the same moment. The VihoX 100 Ton tower was framed for precisely that combination, circulating 78.1 m³/h and standing roughly 2,900 mm across so the fill area can absorb the extra load.

Thermal Path Through the 100T

Two point two kilowatts drives the axial fan, which shifts 42,000 m³/h of air across the pack. Water distribution follows the rotary sprinkler principle used throughout the range, spreading flow evenly so no section of fill dries out. The station is moulded from glass-reinforced plastic over an integrated basin, and a float valve maintains the working level automatically as evaporation and drift remove water.

Thermal Design Conditions

Duty points are stated for entering water at 37 °C and leaving water at 32 °C, giving a 5 °C range at a 27 °C wet-bulb design temperature. Hotter, more humid climates should be checked against the next frame up.

Cooling Tower Specifications — VihoX-100CT

Rated Item VihoX 100T Figure Production Payback
Circulating capacity 78.1 m³/h Absorbs two extruders plus a wider calender
Design pump flow 82.005 m³/h Headroom for a longer, more complex route
Fan motor rating 2.2 kW Higher air volume at the same noise class
Air volume 42,000 m³/h Maintains approach as the load rises
Blade diameter Approx. 1410 to 1800 mm Deep sweep for high-volume air movement
Port size DN125 Lower velocity, less pump energy wasted
Dry weight Approx. 500 kg Plan a crane or forklift for placement
Operating weight Approx. 1,650 kg Reinforce the slab if mounted on a mezzanine
Tower size Approx. Ø2900 × H2370 mm A clear step in footprint over the 80T
Matched pump 11 kW centrifugal One set, vertical or horizontal body

Pairing the 100T With a Co-Extrusion Train

An 11 kW pump covers the 82.005 m³/h design flow at the quoted 20 to 30 m head. Because co-extrusion plants usually run several temperature zones, we suggest splitting the return into a main header and branch lines with individual valves, so the calender stack and the mould manifold stay balanced when one of them changes duty.

Selection and Installation Questions

What makes a 100 ton tower necessary rather than an 80 ton unit?

Two melt streams plus a wider calender simply reject more heat than an 80 ton frame can shed at the same approach. The 100T carries that combined duty without creeping above your process window.

How many cooling circuits can the 100T serve at once?

Typically the calender stack, the embossing roll and two or three mould stations. Add balancing valves so a change on one branch does not disturb the others.

Is the fan noisy on a larger frame?

The 2.2 kW motor turns a wide blade set slowly, so the acoustic signature is closer to a smaller tower than its air volume would suggest.

Can I reuse the pump from an older installation?

Only if its duty point matches roughly 82 m³/h at your measured head. An undersized pump will pull the whole tower off its rated approach.

What water quality does the circuit need?

Clean, reasonably soft water is best. Hard water forms scale on the fill and basin, which reduces heat transfer over time.

Does the tower need a bypass when the line stops?

A bypass keeps flow moving through the pump during short stoppages. For long shutdowns, isolate and drain the tower instead.

How long does commissioning take?

A single tower on a prepared pad is normally running the same day, provided water, power and the pump skid are ready on site.

Can VihoX supply the tower, pump and pipework as one package?

Yes. Most customers order the tower and matched pump together, and we can advise on the header and valve arrangement for your layout.

Discuss a 100 Ton Cooling Package With Our Engineers

Share the melt output of each extruder, the number of downstream stations and the space available, and we will confirm the 100 Ton selection with the margin calculated rather than assumed. Useful background reading: our sheet extrusion line range and the rest of the auxiliary equipment we build.

Talk to the factory: +86 147 7547 6896 · VihoX, Shenzhen, China

Equipment Frequently Ordered With the 100 Ton Tower

A 15HP air-cooled chiller covers the temperature-critical circuits while this frame handles bulk rejection, and compressed air for the same line comes from a 50HP PM VSD screw compressor. The usual host machine is a three-station thermoformer or a larger extrusion train.

Get a QuoteBook a Video Machine TestSend Sample Drawing

Get a Quote for This Machine

Request pricing, technical specs or a video machine test — reply within 24 hours.